CSU Indoor Practice Facility

CSU Indoor Practice Facility

Location: Fort Collins, CO

General Contractor: Saunders Construction

Architects: RATIO Architects, Inc. w/Aller Lingle Architects, PC.

Pre-Engineered Metal Building: Varco Pruden Buildings and Lefever Building Systems

Supply and Erect: Lefever Building Systems

Project Duration: 8 Months – January– August, 2009

Project Cost: $2.5 million

Project Overview and Scope:

  • LBS supplied materials, equipment, and labor for the Varco Pruden structure, roof deck, and other features
  • Employed ¨ translucent wall panels to increase natural light

Key Features:

  • 72,000 SF indoor practice facility for football, softball, basketball, and volleyball
  • Radial roof structure provides a 65 ft. vertical clear height
  • Includes a 70-yard indoor football field, 2 full-sized basketball courts, retractable batting cages, and a  70-yard, 4-lane synthetic running track