Vestas Surface Treatment Building

Vestas Surface Treatment Building

Location: Pueblo, Colorado

General Contractor:  PCL

Project Duration: 9 Months

Supply & Erection: Lefever Building Systems

Total Cost: In excess of $8 million

Project Overview:  

  • LBS Supplied and erected the Pre Engineered Metal buildings and insulated panel systems for the walls and roof of these two structures.  
  • Total square footage of the PEMB project was approximately 186,000 SF.  
  • LBS provided and installed approximately 113,000 SF of insulated wall panels on the 431,000 SF Production Facility Building.
  • Job included all exterior man doors (overhead and main doors) as well as roughly 250 skylights. 
  • Includes supply & installation of a 30 ton bridge crane.
  • Supplied and installed 12 each 26’ x 26’ custom interior doors specifically designed to enhance the internal production flow.
C:\Documents and Settings\Rick - Work\My Documents\LBS Pictures\Project Pictures\Vestas\10.tif
Surface Treatment Building
C:\Documents and Settings\Rick - Work\My Documents\LBS Pictures\Project Pictures\Vestas\32.tif

        Internals Building

Key Building Features:   

  • This is a large production facility for windmill tower production.
  • On the site steel fabrication is performed to convert plate steel into finished support towers for windmill powered generators.
  • Project was completed on a very demanding time schedule to meet production needs.
  • The facility is a very large scale industrial production housing a variety of unique production equipment.