Dairy Farmers of America

Denver, CO

Construction Manager: The Dennis Group
Pre-Engineered Metal Building: Kingspan Insulated Panel Systems
Supply and Erection: Lefever Building Systems
Project Time Frame: Eight months
Total Cost: Approximately $5.5 Million

Project Scope: Lefever Building Systems was the general trades contractor for the shell construction for this plant expansion. In this role, LBS retained and supervised subcontractors in the following areas:

  • Excavation and site prep, site utilities, paving, masonry, structural steel and insulated panel systems, electrical, plumbing, finish work including framing, drywall, painting, flooring, tile, doors and windows, demolition and remodel.
  • Concrete work (foundations, footings, flatwork, site work and exterior paving was self performed by Lefever Building Systems.

Key Project Features: Project was a complex, fast track job that included a water treatment plant, truck scale, 4 bay truck unloading building, milk processing area, employee locker room, break room and administrative area. Also included extensive renovation to existing plant.