Division Headquarters Complex – Increment 1

Larkspur, CO

Project Location: Fort Carson, Colorado 80913
Div. Architect: CH Guernsey & Co.: Oklahoma City
Pre-Engineered Metal Building: VP Buildings
Supply: Lefever Building Systems
Project Time Frame: April 2008 - October 2008

Project Overview:
New Battalion Headquarters Building. 124′ x 113′ x 13′; 3:12 gabled pitched roof with a 20′ x 17’x 13′ covered entry area.

Scope:
New Headquarters building features a Dutch Hip roof; Two rows of SnoBar installed for snow retention. The standing seam roof system included a 20 year finish and weather tightness factory warranty.

Project Highlights:

  • Project met Schedule & Budget Goals.
  • LBS worked with GC on compressed schedule to facilitate erection while working with other subcontractors including masonry work
  • on exterior wall coverings.
  • Includes R30 roof “Cavity” System with Sky Web II for safety/fall protection.