Eckstine Electric Warehouse Expansion

Greeley, CO

General Contractor: Lefever Building Systems
Pre Engineered Metal Building: Varco Pruden Buildings & Lefever Building Systems
Concrete: Lefever Building Systems
Project Duration: July - November 2002
Total Project Cost: Approximately $180,000
Project Scope: Design-Build project, including the concrete work and design, supply, erection of the metal building

Facilities: Project included 7,500 square feet of warehouse & shop space. Eave height 16 feet. End wall expansion to an existing facility.

Key Building Features:

  • Project Size: 7,500 Square Feet – VP Pre Engineered Steel Building
  • Concrete work included a Monolithic slab
  • Supply and erect rigid frame building
  • Includes multiple overhead doors, connections to exiting building
  • Project completed on time and under budget