Johnstown Waste Water Treatment Plant

General Contractor: Hydro Construction
Pre Engineered Metal Building: Varco Pruden Buildings & Lefever Building Systems
Project Time Frame: December 2003 - April 2004
Total Project Cost: Approximately $160,000
Project Scope: Supply and Erect Clarifier, Chemical Storage, Blower, and two Fan Buildings.

Project Details:

  • Installed full height wall and ceiling liner panel.
  • Project on time and under budget

Project Included:

  • Clarifier Building, 80’x 104’x 21′, 8,320 s.f.
  • Chemical Storage Building, 20’x 42’x 13′, 840 s.f.
  • Two Fan Buildings, 16’x 12′ 12′ each, 384 s.f.
  • Blower Building, 16’x 36’x 12′, 576 s.f.