Project General Contractor: Lefever Building Systems
Pre Engineered Metal Building: Chief Industries & Lefever Building Systems
Project Time Frame: August 2003 - January 2004
Project Cost: Approximately $1.0 Million

Project Scope: General Contractor: Design Build project to replace previous facility. LBS provided all design and value engineering input for customer. Included oversight of demolition. Self Performed Concrete work, Supply & Erect Chief pre-engineered metal buildings.

Facilities: Project included 39,200 square foot arena and 8,000 square feet of office, storage and auction/sales area.

Key Building Features:

  • Project Size: 47,280 Square Feet Chief Pre Engineered Metal Building
  • Riding Arena for private ranch
  • Architectural highlights included stone accents, portico entry and accented trim.
  • Stamped concrete entries including custom elk imprint and colored concrete floor provide accent
  • Managed all trades including plumbing, electrical, site work & paving.
  • Interior Steel Studs, Finished Drywall, Tile and Carpet in Office portion.
  • Project met a tight time frame to have facility ready for a major sales event: on time and under budget.