Quail Ridge Dairy

Denver, CO

Concrete Contractor: Lefever Building Systems
Project Time Frame: 10 months

Project Scope: Concrete contractor for five free-stall barns, commodity barn, water treatment tanks as well as multiple “cow highways”. Total project required ten months and covered more than 700,000 square feet of flatwork. Lefever Building Systems poured over 17,000 cubic yards of concrete and managed over 40,000 man hours of labor on site.

Key Project Features: Concrete work included many knee walls, embedment of vertical railing as well as containment curbs and alley scraping system with manure removal channels.