Location: Fort Collins, CO
General Contractor: Saunders Construction
Architects: RATIO Architects, Inc. w/Aller Lingle Architects, PC.
Pre-Engineered Metal Building: Varco Pruden Buildings and Lefever Building Systems
Supply and Erect: Lefever Building Systems
Project Duration: 8 Months – January– August, 2009
Project Cost: $2.5 million
Project Overview and Scope:
- LBS supplied materials, equipment, and labor for the Varco Pruden structure, roof deck, and other features
- Employed ¨ translucent wall panels to increase natural light
Key Features:
- 72,000 SF indoor practice facility for football, softball, basketball, and volleyball
- Radial roof structure provides a 65 ft. vertical clear height
- Includes a 70-yard indoor football field, 2 full-sized basketball courts, retractable batting cages, and a 70-yard, 4-lane synthetic running track