Location: Bennett, CO
General Contractor: Lefever Building Systems
Architect: D2C
Pre-Engineered Metal Building: Varco Pruden Buildings
Supply & Erect: Lefever Building Systems
Project Time Frame: 11 Months
Project Overview and Scope:
- Project scope included total design and construction of 8,500 SF town civic center
- Met strict construction deadlines while constructing during winter conditions
- Implemented multiple design changes and change orders requested by the customer during project completion
Key Features:
- Building includes high-end interior office finish