Broomfield Service Center

Broomfield Service Center

Location: Broomfield, CO

General Contractor: Saunders Construction

Pre-Engineered Metal Building: Varco Pruden Buildings

Supply & Erect: Lefever Building Systems

Project Duration: 9 Months

Project Overview and Scope:

  • Buildings constructed in specific sequence with some structures overlapping
  • Met aggressive schedule and constructed buildings to facilitate activity of other contractors

Key Features:

  • Total of 5 buildings with a total size of 317,000 SF
  • Complex construction features provide great visual appeal